Pan Borneo Highway

Connecting Far-Flung Regions​

HSL and Dhaya Maju Infrastructure (Asia) Sdn Bhd jointly clinched the RM1.6bil project to upgrade and built a section of the Pan Borneo Highway in Sarawak. HSL’s work package seven — commonly referred to in the media as WPC7 — covers Bintangor to Julau (28km), Durin Bridge (1.9km) and Sibu interchange to Sungai Gua Bridge (46km).

Our job includes earthworks, piling, drainage, roads, interchanges, bridges, mechanical and electrical works.

East Malaysia's Dream Infrastructure Comes True

The Pan Borneo Highway is Malaysia’s biggest road project, spanning more than 2,000km. When completed it will connect, Sarawak and Sabah via the Sultanate of Brunei.

Construction of the 1,090km portion in Sarawak is divided into a dozen packages. HSL was a forerunner and was one of the earliest awarded a package.

A Variety of Challenges Leads To A Variety Of Solutions

HSL’s WPC 7 of the highway is among the most challenging. It involves 18 bridges, including a bridge across the Batang Rajang, which is Malaysia’s longest river.

WPC 7 includes two interchanges: a flyover near Julau, and another flyover for seamless travel between Sibu Airport, the town centre and towards Bintulu. The latter interchange is being built in four phases, requiring careful traffic diversion.

There are also 79 bus shelters, seven pedestrian bridges and one lay-by across this span of 76km – all requiring precision engineering and calculations to build.

Doubling Durin Bridge

Durin Bridge, which spans the mighty Batang Rayang, opened in 2006 with two lanes. Because it is an integral part of the Pan Borneo Highway, the bridge is being expanded to accommodate twice the amount of traffic.

HSL’s WPC7 includes creating a new bridge structure that runs parallel to the 1.9km existing bridge.

To achieve that, new support columns are being constructed at the existing piers, without interrupting the flow of traffic.

Senior project manager Philip Lau explains:

“It’s not often you see bridges like this here. Maybe in China, it’s common. Not here. For this bridge, we are using a method called ‘incremental launching’. There are a total of 16 pile caps that provide the new road section with its stability, drilled right into the banks of the Rajang River. The concrete mat layers are then filled up using special ‘hammerhead’ building casts, creating the structural columns for the new bridge portion.

“Once it’s set, we push it outwards to meet the four piers in the river.”

Safety officers also ensure that motorists are able to use the bridge safely as work continues.

Industrial continues to grow everyday thanks to the confidence our clients have in us.

Balance Life Work

Safety is one of the highest priorities within Industrio. And the company will keep it that way.

Cost-effective Industrial Solutions

Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Robust Inventory of Parts and Products

Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

WordPress Appliance - Powered by TurnKey Linux